Severnside Energy Recovery

  • Location:  Avonmouth
  • Client:  William Hare
  • Main:  McAlpines/Hitachi
  • Tonnage:  1500 tonnes
Scope of Work: Erection of envelope steel covering Waste Bunker, Tipping Hall, Boiler Structure, Flue Gas and Turbine Hall. This involved assembling as much steel as possible to be erected as modules, this included pairs of trusses with cladding rails and purlins all assembled weighing 50tns and being lifted to a height of over 50m with 500tn mobiles cranes. All bunker steel was was connected to fin plates welded by CSE to a 30m high concrete core.